See Weston's Summer Public Works Project Schedule
Weston has released a schedule of summer road projects, which you can find below.
(Source: Weston town hall announcement).
POND BROOK CIRCLE DRAINAGE PROJECT:
Monday, July 22nd – Water Main Replacement Begins
Find out what's happening in Westonwith free, real-time updates from Patch.
TRANSFER STATION BRIDGE:
Find out what's happening in Westonwith free, real-time updates from Patch.
Monday, July 22 – Pre bridge removal work – wetlands replication, Stony Brook stream diversion.
Monday, Aug. 5 – Transfer Station Closes for 2 week bridge replacement.
PAVING SCHEDULE:
Monday, Aug. 5 - Thursday Aug. 8 – road reclamation Hobbs Brook Road and Forest Ridge Road. Base course of paving to follow.
Thursday, Aug. 8 - Friday, Aug. 9 – road reclamation on Maple Road. Base course of paving and sidewalk reconstruction to follow.
Monday, Aug. 12 - Friday, Aug. 16 – road reclamation on Trailside Road, Beech Road and Colonial Way. Base course of paving and sidewalk reconstruction to follow.
Monday, Aug., 19 – road reclamation at Linwood Cemetery. Base course of paving to follow.
Date to be determined -- Transfer Station and MBTA Commuter Rail Parking Area Pavement Reconstruction.